Metro rail witnesses 72.99 percent overall progress

The Report Desk

Published: December 5, 2021, 10:18 PM

Metro rail witnesses 72.99 percent overall progress

The overall progress of construction work of 21.26-kiolomtere-long elevated metro rail service from Uttara to Motijheel-Kamalapur Railway stands at 72.99 percent now, while 89.88 percent civil work between Uttara and Agargaon has been done.

“At present, 11.73 kilometer viaduct, station column and other related works of metro rail between Uttara and Agargaon have been completed,” Managing Director of Dhaka Mass Transit Company Ltd (DMTCL) MAN Siddique said Sunday (December 5).

He said construction work of Mass-Rapid Transport (MRT) Line-6, the country’s first elevated metro rail system in Dhaka city under the Fast Track projects, is going on in full swing targeting to open it for commercial operation by next year.

Siddique said the metro train undertaken by Prime Minister Sheikh Hasina, began its mainline performance test on viaduct in October, which will require six months.

“Before commercial run of the metro rail we have to carry out integrated test and trial run,” he added.

According to the project details, the 8th set of metro train reached the Mongla port, while 9th and 10th shipment of metro train set will reach the country in January, 2022.

The total 21.26-kilomtere metro-rail project is being built in eight packages. The overall physical progress of the first phase construction from Uttara to Agargaon is 89.88 percent and second phase progress from Agargaon to Motijheel is 71.82 percent, while the overall progress stood at 72.99 percent.